Spring Construction Update
Spring Construction Update
Posted on 04/24/2018
Corner of new CKHS

Status: A roof is going over the middle school. Framing and protective covering are going up on the exterior of both schools. Fire protection, HVAC, plumbing, and electrical rough-in work is in progress. Crews have started grading the new high school football field and track.

What’s next: Crews plan to put the steel up for the new career and technical education building after Memorial Day.